Core Business General Contracting of Industrial & Utility & Process Plant Projects

General Contracting of Industrial & Utility & Process Plant Projects

E-mail Print PDF
1. Establishment of Common Facilities of Damavand Power Plant

Client : Iran Power Development Company (IPDC)
Location :
Damavand (Tehran Province)
Duration :
12 months
Delivery Method :
PCC
Contract Date :
Sep. 2009
Description :
5 fuel storage tanks, fire water pump station, auxiliary boiler, underground fire water tank, foundations of equipment, piping, pit condense, pipe & cable trench, oil & water separation basin, access road, fire protection system, earthing, electrical, instrument and mechanical equipment.
Status : Provisional Acceptance Certificate.

2. Installation & Commissioning of Poly Propylene Unit of Maroon Petrochemical
Client : Maroon Petrochemical Company
Location : Mahshahr (Khoozestan Province)
Duration : 11 months
Delivery Method : C
Contract Date : May 2003
Description : 2000 MT equipment, 110'000 dia/inch piping, 1000 MT erection of steel structures, completion of remaining civil works, 270 MT welding & erection , installation of electrical & instruments, fire alarm & protection systems, earthing & cathodic protection
Status : Final Acceptance Certificate
3. Establishment of Pars Carbon Black Factory Extension Unit
Client : Pars Carbon Black Company
Location :
Saveh (Markzai Province)
Duration :
24 months
Delivery Method :
EPCC
Contract Date :
Jul. 2003
Description :
15'000 MT/y production capacity of soft & hard grade carbon, feed grade unit, soft & hard grade reactors, collection & separation units, granulation unit, storage & silo units, packing & loading unit, water recycling system, vacuum cleaning system and utilities
Status : 
Final Acceptance Certificate
4. Installation & Commissioning of Oxygen & Compressed Air Production Unit

Client : Khorasan Steel Complex
Location : Neyshabur (Khorasan Province)
Duration : 12 months
Delivery Method : C
Contract Date : Oct. 1999
Description : Installation and commissioning of all equipment of a 4800 Nm3/hr of an oxygen plant including a 45 MT Cold Bo
Status : Final Acceptance Certificate
5. Establishment of Bulk Handling Equipments of Raw Materials Store - Balancing Program

Client : Esfahan Steel Co.
Location : Esfahan
Duration : 16 months
Delivery Method : EPC
Contract Date : Mar. 2008
Description : Stackers, reclaimers, conveyors, rails , electrical, control systems and relevant steel structures
Status : Final Acceptance Certificate
  •  
6. Installation of Mill Area and Roll Workshop

Client : Khoozestan Oxin Steel
Location : Ahwaz (Khoozestan Province)
Duration : 12 months
Delivery Method : C
Contract Value : Oct. 2007
Description : Installation, erection, pressure test, welding of 65'000 inch-dia, piping and fittings, 6700 MT equipments, motors, 70'000 MT support and instruments
Status : Final Acceptance Certificate
7. Installation & Commissioning of of Salman Farsi Sugar Factory Equipment

End User : Sugar Cane Development and By-products Commercial Co.
Client : Falegh Sanat
Location : Khorramshahr (Khuzestan Province)
Duration : 18 months
Delivery Method : C
Contract Date : Mar. 2003
Description: Manufacturing and installation of 6 sets of cutting machines (82 MT), belt and chain conveyors (1030 MT), mills, 6 sets of shredders (140 MT), 69 sets of Rollers, gantry cranes (10 and 40 MT) and other relevant equipment
Status : Final Acceptance Certificate
 
8. Establishment of Pipe Production Factory

Client : Sadid Industrial Group
Location : Mahshahr (Khoozestan Province)
Duration : 12 months
Delivery Method : PC
Contract Value : Apr. 2002
Description : Procurement, installation and commissioning of pipe manufacturing equipment including loading, unloading and pipe transfer systems, pipe welding machine and steel structure of factory
Status : Final Acceptance Certificate
9. Establishment of Water Treatment and Water Transfer Pipeline

Client : Semnan Regional Water Co.
Location : Damghan (Semnan Province)
Duration : 24 months
Delivery method : PC
Contract Date : Oct. 2009
Description : Procurement, construction and commissioning of a water treatment system and a water transfer pipeline from a dam – 5 km far from Damghan – to water reservoir of Damghan. The water treatment system includes physical, chemical and biological treatment of intake water to reduce the concentration of contaminants, so the water becomes fit for its dsired end-use. It also consists of establishment and all relevant civil works of settling tanks or sumps, chlorine injection tank, repair shop, pulsators, slow sand filters, operation, recovery, security, administration, diesel generator, aeration sludge lagoons, flash mixer, chloror ferric tanks and valves. The pipeline is a 20" UPVC at 4945 m pipe length.
Status : Provisional Acceptance Certificate
 

10. Air Separation Unit ASU

Client : Arvand Petrochemical Co
Location : PET Zone Site 3 Mahshahr
Duration : 4 months
Delivery Method : EPC
Contract Date : April. 2011
Description : Design & Construction of Air Separation Unit ASU
Status : Provisional Acceptance Certificate

11. Design & Manufacturing of hit Exchanger Tower for Ghatran Refinery

Client : Coal Tar Refinery (C.T.R. CO)
Location : Isfahan Province
Duration : 7 months
Delivery Method : EPC
Contract Date : Nov. 2009
Description : Design & Manufacturing of hit Exchanger Tower for Ghatran Refinery
Status : Provisional Acceptance Certificate

12. Establishment of Bibi Hakimeh-1 Desalting Unit

Client : National Iranian South Oil Company (NISOC)
Location :
Bibi Hakimeh Industrial Zone (Booshehr Province)
Duration :
36 months
Delivery Method :
EPCC, JV with Tehran Berkeley
Contract Date :
Apr. 2008
Description :
Desalting of 55'000 bpd crude oil including three phase gas separators, heat exchangers, pump stations , oil pre-heaters, oil desalting & dehydration unit, wastewater treatment unit, 86 barg water injection unit, 40 km water transfer pipeline 6" and 750 m oil transfer pipeline 12"
Status :
Mechanical completion

13. Establishment of Open-loop Cooling Water System of Ab Zamzam-1

Client : Khoozestan Steel Co.
Location : Ab-zamzam-1, Khoozoestan Steel, Ahwaz (Khoozestan Province)
Duration : 18 months
Delivery method : EPCC
Contract Date : Apr. 2010
Description : Cooling water system, water distribution network, pump house, MCC house, diesel generator house, access road, contaminated cooling tower 2200 m3/hr, clarifiers & feed chamber 3200 m3/hr, under flow pump access tunnel & chemical room, sedimentation basin, pipe racks, trenches  mechanical, electrical, instruments and civil works
Status : In progress
14. Establishment of Oxygen Production Plant

Client : National Iranian Copper Industries Co. (NICICO)
Location : Rafsanjan (Kerman Province)
Duration : 24 months
Delivery Method : EPCC, JV with SIAD (Italy)
Contract Date : Sep. 2008
Description : 10,000 Nm3/hr capacity, 95.5% oxygen purity
Status : Provisional Acceptance Certificate
15. Establishment of Closed-loop Cooling Water & Water Treatment System

Client : Abadan Oil Refining . (AORC)
Location : Abadan (Khoozestan Province)
Duration : 24 months
Delivery Method : EPCC, consortium with Omrab company
Contract Date : Apr. 2008
Description : 36'000 m3/hr cooling tower, water intake equipment, water distribution network, pre-treatment system, chemical dosing station, surface condenser, reverse osmosis WTP, clarifiers, storage tanks and ancillaries, fire fighting system and HP steam transfer line
Status : Provisional Acceptance Certificate
 
16. Establishment of Sea Water Intake of LNG Refinery

Client : Iran LNG Co.
Location : Assaluyeh (Booshehr Province)
Duration : 24 months
Delivery Method : EPCC
Contract Date : 2010
Description : Offshore intake headers, submarine intake pipeline, onshore pumping basin, 134'000 m3/hr flow rate, sluice gates, bar screens, inlet & outlet stop logs, inlet & outlet guidance sets, trash racking machine and cranes
Status : In progress

17. Establishment of Air and N2 Generation Unit of LNG Refinery

Client : Iran LNG Co.
Location : Assaluyeh (Booshehr Province)
Duration : 10 months
Delivery Method : EPCC, JV with Cryonorm (NL)
Contract Date : 2011
Description : 2000 Nm3/hr N2, 200 Nm3/hr plant air and 12'000 Nm3/hr instrument air capacity
Status : Just started
No picture available!

18. Establishment of Copper Flash Smelting Unit

Client : National Iranian Copper Industries Co. (NICICO)
Location : Sarcheshmeh (Kerman Province)
Duration : 42 months
Delivery Method : EPCC, consortium with Monia, Bamrah and Fakoor companies
Contract Value : Dec. 2010
Description : A flash smelting plant with production capacity of 875 MT/day cathodic copper from copper concentrate including flux preparation & storing unit, material handling system, smelting unit, dryer, flash smelting furnace, FSF handling & dust collection system, anode furnace and cooling water system 
Status : In progress

19. Establishment of Copper Refinery of Khatoon Abad

Client : National Iranian Copper Industries Co. (NICICO)
Location : Khatoon Abad (Kerman Province)
Duration : 30
Delivery Method : EPCF, consortium with Fakoor Sanat Tehran and Ronin companies
Technolog : EPCM (Canada)
Contract Date : Jul. 2000
Description : A copper refinery as supplementary of existing sarcheshmeh Copper Complex with production capacity of 200'000 MT/day including cathodic blanks, cathode washing and stripping system, anode preparation system, anode scrap wash system, transformer rectifier, copper bus bar system, tankhouse crane, electrolitic cells, cell-top hardware, electrolyte filters, electrolyte heat exchangers, polishing filters, process tanks, process pumps and process valves
Status : In progress

20. Gas Transfer Pipe Line Damghan/ Neka

Client : Iran Gas Engineering and Developing Co.
Location : Semnan & Mazandaran Provinces of Iran
Duration : 24 Month
Delivery Method : PCF, JV With Tana Energy and Payssa
Technolog : PC
Contract Date : March. 2013
Description : 42” Gas Transfer Pipe Line Ghooshe Damghan/ Kiasar/ Sari/ Neka and Associated Establish-Ment
Status : In progress

21. Gondole Sazi Gohar Zamin

Client : Gohar Zamin Corporation
Location : Sirjan Gohar Zamin Complex
Duration : 24 Month
Delivery Method : EPC, JV With Asfalt Toos
Technolog :EPC
Contract Date : February. 2014
Description : Construction of 5 Million Ton Pellet Factory by Using Loregy Technology.
Status : In progress